Bus Station

Site A CSO located under a new bus station development.

Objective To install a new hydraulic operated CSO screen complete with a free issue control panel.

Solution We undertook the design, specification and liaison between ourselves, the screen manufacturer and the control panel manufacturer. The system was a key element of the overall development, and was installed, cabled and commissioned by ourselves to meet the client’s program.

Notes The installation was completed within program comprising of two elements, which included temporary and permanent works to facilitate the civil construction.